Heatherton Bridge
Federal contribution
$1.8M
$1,800,000
Federal share50%
of $3.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 30, 2010
2009201120132015
Built
Approved 13 months before the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Province of Nova Scotia
- Construction start
- May 27, 2014(actual)
- Construction end
- Sep 15, 2015(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Jun 30, 2014
- Construction end18 months earlyforecast Mar 31, 2017
Also in Antigonish
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29865 in the federal list. How to read these figures.