Updating water treatment plants in Baie-Comeau

Baie-Comeau, Quebec

completeDrinking WaterMIC
Federal contribution
$19.9M
$19,921,500
Federal share42%

of $47.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 21, 2009
201020132016201920222025
Built

Approved 2 months after the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Ultimate recipient
City of Baie Comeau
Construction start
Jul 1, 2014(actual)
Construction end
Nov 14, 2024(actual)

Against the original forecast

  • Construction end3.9 years lateforecast Dec 31, 2020