Replacement of the outer casing including metal cladding, insulation, doors and windows
Federal contribution
$1.0M
$1,023,772
Federal share80%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
2022
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré de santé et de services sociaux de la Côte-Nord
- Construction start
- May 10, 2021(actual)
- Construction end
- Apr 22, 2022(actual)
Against the original forecast
- Construction start4 weeks lateforecast Apr 12, 2021
- Construction end4 months lateforecast Dec 31, 2021
Also in Baie-Comeau
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58903 in the federal list. How to read these figures.