Art Gallery of Saskatchewan (Previously Destination Centre)
Federal contribution
$13.0M
$13,020,000
Federal share19%
of $68.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 23, 2009
ApprovedJul 16, 2010
2010201220142016
Built
Approved 10 months after the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- City of Saskatoon
- Construction start
- Apr 18, 2013(actual)
- Construction end
- Mar 22, 2017(actual)
Against the original forecast
- Construction end7 weeks lateforecast Jan 31, 2017
Also in Saskatoon
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29907 in the federal list. How to read these figures.