Saskatoon Flood Control

Saskatoon, Saskatchewan

completeWastewaterMIC
Federal contribution
$2.5M
$2,525,852
Federal share32%

of $7.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 9, 2011
20112012201320142015
Built

Approved 10 months before the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Ultimate recipient
City of Saskatoon
Construction start
Aug 15, 2011(actual)
Construction end
Jul 31, 2015(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Aug 31, 2015