Edmonton North Light Rail Transit Expansion
Federal contribution
$100.0M
$100,000,000
Federal share20%
of $491.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 15, 2013
2012201320142015
Built
Approved 2.4 years before the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- City of Edmonton
- Construction start
- Jun 1, 2011(actual)
- Construction end
- Sep 6, 2015(actual)
Against the original forecast
- Construction start3 months lateforecast Mar 1, 2011
- Construction end6 months lateforecast Mar 15, 2015
Also in Edmonton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29909 in the federal list. How to read these figures.