Grain Storage Expansion
Edwardsburgh/Cardinal, Ontario
Federal contribution
$1.8M
$1,841,417
Federal share33%
of $5.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedOct 16, 2009
ApprovedJan 4, 2010
20102011
Built
Approved 3 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Edwardsburgh/Cardinal
- Construction start
- Oct 19, 2009(actual)
- Construction end
- Jun 10, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast Sep 11, 2009
- Construction end2 months lateforecast Mar 31, 2011
Also in Edwardsburgh/Cardinal
- Cardinal County Road 2 Watermain Replacement$844.1K
- Cardinal Waterfront Multi-Use Path$80.0K
- Rehabilitate exterior overcoat of the existing Elevated Tank shell and cone surfaces.$70.0K
- Replace Ultraviolet (UV) unit at the wastewater treatment plant$35.8K
- Replace piping, valves and measuring device at Adelaide Street Pumping Station Dry Well$29.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29942 in the federal list. How to read these figures.