Rehabilitate exterior overcoat of the existing Elevated Tank shell and cone surfaces.
Edwardsburgh/Cardinal, Ontario
Federal contribution
$70,000
Federal share50%
of $140.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Edwardsburgh/Cardinal
- Construction start
- Sep 25, 2017(actual)
- Construction end
- Oct 13, 2017(actual)
Against the original forecast
- Construction start5 months lateforecast May 1, 2017
- Construction end7 weeks earlyforecast Nov 30, 2017
Also in Edwardsburgh/Cardinal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49097 in the federal list. How to read these figures.