Fire Station #2 Replacement (Fenwick)
Federal contribution
$907,350
Federal share31%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Pelham
- Construction start
- Sep 30, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start4 months lateforecast May 31, 2010
- Construction end5 months lateforecast May 31, 2011
Also in Pelham