Fire Station #2 Replacement (Fenwick)

Pelham, Ontario

completeAdministration, Emergency and Public WorksISF
Federal contribution
$907,350
Federal share31%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Pelham
Construction start
Sep 30, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start4 months lateforecast May 31, 2010
  • Construction end5 months lateforecast May 31, 2011