Construction of splash pad in Centennial Park

Pelham, Ontario

completeActive TransportationCVRIS
Federal contribution
$89,865
Federal share80%

of $112.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
2022
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Town of Pelham
Construction start
Sep 1, 2021(actual)
Construction end
Jul 6, 2022(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Aug 1, 2022