Denfield Operations Centre
Federal contribution
$1.8M
$1,792,293
Federal share30%
of $6.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Middlesex Centre
- Construction start
- Jun 10, 2010(actual)
- Construction end
- Jan 28, 2011(actual)
Against the original forecast
- Construction end4 weeks lateforecast Dec 31, 2010
Also in Middlesex Centre
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29951 in the federal list. How to read these figures.