Denfield Operations Centre

Middlesex Centre, Ontario

completeAdministration, Emergency and Public WorksISF
Federal contribution
$1.8M
$1,792,293
Federal share30%

of $6.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jun 10, 2010(actual)
Construction end
Jan 28, 2011(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Dec 31, 2010