Back to projects

Construction of Cycling Infrastructure Medway Road

Middlesex Centre, Ontario

completeActive TransportationCVRIS
Federal contribution
$168,703
Federal share80%

of $210.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
County of Middlesex
Construction start
Sep 13, 2021(actual)
Construction end
Dec 1, 2021(actual)

Also in Middlesex Centre

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60005 in the federal list. How to read these figures.