Churchill Line Rehabilitation

Brooke-Alvinston, Ontario

completeHighways and RoadsISF
Federal contribution
$75,000
Federal share33%

of $225.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jul 6, 2009(actual)
Construction end
Oct 28, 2009(actual)

Against the original forecast

  • Construction start3 months earlyforecast Oct 15, 2009
  • Construction end3 months earlyforecast Jan 15, 2010