Back to projects

Provide Potable Water to the Visitors Information Centre

Marathon, Ontario

completeDrinking WaterISF
Federal contribution
$18,000
Federal share33%

of $54.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Marathon
Construction start
May 1, 2010(actual)
Construction end
Oct 31, 2010(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Jun 1, 2010
  • Construction end4 weeks lateforecast Sep 30, 2010

Also in Marathon

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29969 in the federal list. How to read these figures.