Back to projects

Rehabilitation of Line 26

Perth South, Ontario

completeHighways and RoadsISF
Federal contribution
$270,288
Federal share29%

of $948.1K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Perth South
Construction start
Sep 16, 2009(actual)
Construction end
Jul 20, 2010(actual)

Against the original forecast

  • Construction end3 weeks lateforecast Jun 30, 2010