Rehabilitation of the Administrative Office
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
202220232024
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Perth South
- Construction start
- Sep 12, 2023(actual)
- Construction end
- Mar 11, 2024(actual)
Against the original forecast
- Construction start2.3 years lateforecast Jun 1, 2021
- Construction end7 weeks earlyforecast Apr 30, 2024
Also in Perth South
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59717 in the federal list. How to read these figures.