New Windows for Old Mill building
Federal contribution
$28,002
Federal share32%
of $87.5K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Billings
- Construction start
- Aug 1, 2009(actual)
- Construction end
- Nov 1, 2009(actual)
Against the original forecast
- Construction end5 months earlyforecast Mar 31, 2010