New Windows for Old Mill building

Billings, Ontario

completeCultureISF
Federal contribution
$28,002
Federal share32%

of $87.5K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Billings
Construction start
Aug 1, 2009(actual)
Construction end
Nov 1, 2009(actual)

Against the original forecast

  • Construction end5 months earlyforecast Mar 31, 2010

Also in Billings

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29980 in the federal list. How to read these figures.