Shoreline Stabilization: Kagawong Low-Lift Station

Billings, Ontario

completeDisaster MitigationCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 7, 2021
202220232024
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Township of Billings
Construction start
Sep 29, 2023(actual)
Construction end
Dec 14, 2023(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Sep 15, 2023
  • Construction end10 months earlyforecast Sep 30, 2024

Also in Billings

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59622 in the federal list. How to read these figures.