Road Rehabilitation Program - Cambridge

Cambridge, Ontario

completeHighways and RoadsISF
Federal contribution
$4.2M
$4,166,667
Federal share33%

of $12.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Cambridge
Construction start
Jun 30, 2009(actual)
Construction end
Nov 23, 2010(actual)

Against the original forecast

  • Construction end4 months earlyforecast Mar 31, 2011

Also in Cambridge

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30008 in the federal list. How to read these figures.