Highway 401 Widening - Hespeler Rd. to Townline Rd.
Federal contribution
$96.0M
$96,030,979
Federal share50%
of $192.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 27, 2017
today
2017202020232026
BuiltForecast
Approved 3 months before the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Ontario Ministry of Transportation
- Construction start
- May 1, 2020(actual)
- Construction end
- Nov 30, 2027(forecast)
Against the original forecast
- Construction start23 months lateforecast Jun 1, 2018
Also in Cambridge
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46656 in the federal list. How to read these figures.