Renewal of Base Line Bridge Over Little Bear Creek East

Chatham, Ontario

completeHighways and RoadsISF
Federal contribution
$629,300
Federal share27%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 30, 2010(actual)
Construction end
Sep 1, 2011(actual)

Against the original forecast

  • Construction start5 months lateforecast Apr 1, 2010
  • Construction end7 weeks lateforecast Jul 15, 2011

Also in Chatham

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30060 in the federal list. How to read these figures.