Upgrade Membrane Cassettes at Little Current Water Plant
Northeastern Manitoulin and The Islands, Ontario
Federal contribution
$166,603
Federal share33%
of $499.8K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Northeastern Manitoulin and The Islands
- Construction start
- Nov 1, 2009(actual)
- Construction end
- Jan 21, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast Oct 1, 2009
- Construction end5 months earlyforecast Jun 30, 2010
Also in Northeastern Manitoulin and The Islands
- Green Bush Road Rehabilitation$290.4K
- NEMI Recreation Center Air Conditioner Upgrade$80.0K
- Indian Mountain Road Upgrade$74.6K
- Relocation and Replacement of Membrane Programmable Logic Controller (PLC) at the Little Current Water Treatment Plant$50.0K
- Rehabilitation of Generator and Transfer Switch at the Little Current Main Pump House$15.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30153 in the federal list. How to read these figures.