Relocation and Replacement of Membrane Programmable Logic Controller (PLC) at the Little Current Water Treatment Plant
Northeastern Manitoulin and The Islands, Ontario
Federal contribution
$50,000
Federal share33%
of $150.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
20182019
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Northeastern Manitoulin and the Islands
- Construction start
- Oct 31, 2017(actual)
- Construction end
- Dec 31, 2018(actual)
Against the original forecast
- Construction start6 months lateforecast May 1, 2017
- Construction end14 months lateforecast Oct 31, 2017
Also in Northeastern Manitoulin and The Islands
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48524 in the federal list. How to read these figures.