Relocation and Replacement of Membrane Programmable Logic Controller (PLC) at the Little Current Water Treatment Plant

Northeastern Manitoulin and The Islands, Ontario

completeDrinking WaterCWWF
Federal contribution
$50,000
Federal share33%

of $150.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
20182019
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Oct 31, 2017(actual)
Construction end
Dec 31, 2018(actual)

Against the original forecast

  • Construction start6 months lateforecast May 1, 2017
  • Construction end14 months lateforecast Oct 31, 2017

Also in Northeastern Manitoulin and The Islands

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48524 in the federal list. How to read these figures.