Road Rehabilitation

Kitchener, Ontario

completeHighways and RoadsISF
Federal contribution
$822,760
Federal share20%

of $4.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 17, 2009(actual)
Construction end
Oct 29, 2009(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 1, 2009
  • Construction end2 months earlyforecast Dec 31, 2009

Also in Kitchener