County Road 22 Improvement Program
Federal contribution
$2.6M
$2,600,791
Federal share33%
of $7.9M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built
Approved 22 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- County of Essex
- Construction start
- Oct 19, 2009(actual)
- Construction end
- Nov 30, 2010(actual)
Against the original forecast
- Construction start5 weeks lateforecast Sep 15, 2009
- Construction end4 months earlyforecast Mar 30, 2011
Also in Lakeshore
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30394 in the federal list. How to read these figures.