County Road 22 Improvement Program

Lakeshore, Ontario

completeHighways and RoadsISF
Federal contribution
$2.6M
$2,600,791
Federal share33%

of $7.9M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built

Approved 22 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
County of Essex
Construction start
Oct 19, 2009(actual)
Construction end
Nov 30, 2010(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Sep 15, 2009
  • Construction end4 months earlyforecast Mar 30, 2011