Back to projects

Emergency Medical Services Base - Lakeshore

Lakeshore, Ontario

completeOtherISF
Federal contribution
$466,667
Federal share33%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 8, 2011
2011
Built

Approved 8 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
County of Essex
Construction start
Feb 1, 2011(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Dec 1, 2010

Also in Lakeshore