Back to projects

Replacement of Four Large Culverts

Sables-Spanish Rivers, Ontario

completeHighways and RoadsISF
Federal contribution
$199,506
Federal share27%

of $750.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jun 21, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start8 months lateforecast Nov 1, 2009
  • Construction end4 weeks lateforecast Sep 30, 2011