Rehabilitation Project involving the Relining of Water Storage Tower that supports the Water Treatment System serving 500 Customers

Sables-Spanish Rivers, Ontario

completeDrinking WaterCWWF
Federal contribution
$50,000
Federal share35%

of $143.0K total eligible cost; the rest comes from other partners.

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jun 12, 2017(actual)
Construction end
Jul 17, 2017(actual)

Against the original forecast

  • Construction start6 weeks lateforecast May 1, 2017
  • Construction end2 months earlyforecast Sep 30, 2017