Rehabilitation Project involving the Relining of Water Storage Tower that supports the Water Treatment System serving 500 Customers
Sables-Spanish Rivers, Ontario
Federal contribution
$50,000
Federal share35%
of $143.0K total eligible cost; the rest comes from other partners.
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Sables-Spanish Rivers
- Construction start
- Jun 12, 2017(actual)
- Construction end
- Jul 17, 2017(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 1, 2017
- Construction end2 months earlyforecast Sep 30, 2017
Also in Sables-Spanish Rivers
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48438 in the federal list. How to read these figures.