Belle Vallee Road - Gravel Resurfacing

Harley, Ontario

completeHighways and RoadsISF
Federal contribution
$85,661
Federal share33%

of $258.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Harley
Construction start
Aug 31, 2009(actual)
Construction end
Nov 5, 2010(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jul 6, 2009
  • Construction end5 weeks lateforecast Sep 30, 2010

Also in Harley

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30440 in the federal list. How to read these figures.