Belle Vallee Road - Gravel Resurfacing
Federal contribution
$85,661
Federal share33%
of $258.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Harley
- Construction start
- Aug 31, 2009(actual)
- Construction end
- Nov 5, 2010(actual)
Against the original forecast
- Construction start8 weeks lateforecast Jul 6, 2009
- Construction end5 weeks lateforecast Sep 30, 2010