Replacement of the Roy Bridge

Harley, Ontario

completeHighways and RoadsRNIS
Federal contribution
$2.7M
$2,684,219
Federal share60%

of $4.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 6, 2020
20212022
Built

Approved 3 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Township of Harley
Construction start
Mar 1, 2022(actual)
Construction end
Jul 28, 2022(actual)

Against the original forecast

  • Construction start10 months lateforecast May 3, 2021
  • Construction end4 weeks lateforecast Jun 30, 2022