Replacement of the Roy Bridge
Federal contribution
$2.7M
$2,684,219
Federal share60%
of $4.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 6, 2020
20212022
Built
Approved 3 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Township of Harley
- Construction start
- Mar 1, 2022(actual)
- Construction end
- Jul 28, 2022(actual)
Against the original forecast
- Construction start10 months lateforecast May 3, 2021
- Construction end4 weeks lateforecast Jun 30, 2022
Also in Harley