Road Rehabilitation

Frontenac Islands, Ontario

completeHighways and RoadsISF
Federal contribution
$342,333
Federal share33%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Sep 28, 2009(actual)
Construction end
Aug 29, 2011(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 15, 2009
  • Construction end2 months earlyforecast Oct 31, 2011

Also in Frontenac Islands

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30506 in the federal list. How to read these figures.