Wolfe Island Wind Plant - Haul Roads Rehabilitation (Stage 2)
Federal contribution
$158,666
Federal share33%
of $476.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Frontenac Islands
- Construction start
- Oct 1, 2009(actual)
- Construction end
- Aug 29, 2011(actual)
Against the original forecast
- Construction start3 months earlyforecast Dec 31, 2009
- Construction end5 weeks earlyforecast Sep 30, 2011
Also in Frontenac Islands
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30577 in the federal list. How to read these figures.