Wolfe Island Wind Plant - Haul Roads Rehabilitation (Stage 2)

Frontenac Islands, Ontario

completeHighways and RoadsISF
Federal contribution
$158,666
Federal share33%

of $476.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Oct 1, 2009(actual)
Construction end
Aug 29, 2011(actual)

Against the original forecast

  • Construction start3 months earlyforecast Dec 31, 2009
  • Construction end5 weeks earlyforecast Sep 30, 2011

Also in Frontenac Islands

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30577 in the federal list. How to read these figures.