Al Palladini Community Centre - New Elevator Installation
Federal contribution
$97,898
Federal share33%
of $300.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Vaughan
- Construction start
- Dec 9, 2009(actual)
- Construction end
- Jun 8, 2010(actual)
Against the original forecast
- Construction start6 months earlyforecast Jun 1, 2010
- Construction end4 months earlyforecast Sep 30, 2010