Back to projects

Road Rehabilitation - Carleton Place

Carleton Place, Ontario

completeHighways and RoadsISF
Federal contribution
$716,667
Federal share33%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Carleton Place
Construction start
Jul 1, 2009(actual)
Construction end
Sep 21, 2011(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Jul 15, 2009
  • Construction end6 weeks earlyforecast Oct 31, 2011

Also in Carleton Place