Road Rehabilitation - Carleton Place
Federal contribution
$716,667
Federal share33%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Carleton Place
- Construction start
- Jul 1, 2009(actual)
- Construction end
- Sep 21, 2011(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Jul 15, 2009
- Construction end6 weeks earlyforecast Oct 31, 2011
Also in Carleton Place