Lanark Community Programs - Bennett Street Facilities Development

Carleton Place, Ontario

completeOtherISF
Federal contribution
$550,000
Federal share31%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 21, 2009
20102011
Built
Program
Infrastructure Stimulus Fund
Construction start
Sep 19, 2010(actual)
Construction end
Jun 26, 2011(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Sep 1, 2010
  • Construction end2 months earlyforecast Aug 31, 2011