Maple Community Centre

Vaughan, Ontario

completeRecreationISF
Federal contribution
$100,000
Federal share33%

of $300.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Vaughan
Construction start
Dec 20, 2009(actual)
Construction end
Apr 9, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Dec 1, 2009

Also in Vaughan

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30557 in the federal list. How to read these figures.