Nort Johnson Park - Installation of Walkway Lighting

Vaughan, Ontario

completeActive TransportationISF
Federal contribution
$64,360
Federal share26%

of $250.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Vaughan
Construction start
Dec 15, 2009(actual)
Construction end
Apr 9, 2010(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Dec 1, 2009
  • Construction end3 weeks lateforecast Mar 19, 2010