24th Street West Drainage Improvements
Federal contribution
$145,684
Federal share30%
of $490.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Georgian Bluffs
- Construction start
- Oct 1, 2009(actual)
- Construction end
- Dec 31, 2009(actual)
Against the original forecast
- Construction start3 months lateforecast Jul 6, 2009