Upgrade aging components of Shallow Lake Water Plant

Georgian Bluffs, Ontario

completeDrinking WaterCWWF
Federal contribution
$87,847
Federal share49%

of $178.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 16, 2017
201820192020
Built

Approved 4 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Georgian Bluffs
Construction start
Jul 2, 2017(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start6 weeks lateforecast May 20, 2017
  • Construction end18 months earlyforecast Sep 30, 2021

Also in Georgian Bluffs

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50119 in the federal list. How to read these figures.