Back to projects

Kerwood Fire Hall

Adelaide-Metcalfe, Ontario

completeAdministration, Emergency and Public WorksISF
Federal contribution
$196,569
Federal share33%

of $600.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Oct 12, 2009(actual)
Construction end
Aug 10, 2010(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Sep 1, 2009
  • Construction end4 months earlyforecast Dec 15, 2010

Also in Adelaide-Metcalfe

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30619 in the federal list. How to read these figures.