Kerwood Park Facilities Upgrade
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Adelaide-Metcalfe
- Construction start
- Sep 7, 2021(actual)
- Construction end
- Mar 1, 2022(actual)