Lake Park Road Reconstruction
Federal contribution
$300,178
Federal share33%
of $900.5K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Beckwith
- Construction start
- Jun 25, 2010(actual)
- Construction end
- Nov 1, 2010(actual)
Against the original forecast
- Construction start3 months lateforecast Apr 1, 2010
- Construction end5 weeks lateforecast Sep 30, 2010