Back to projects

Lake Park Road Reconstruction

Beckwith, Ontario

completeHighways and RoadsISF
Federal contribution
$300,178
Federal share33%

of $900.5K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Beckwith
Construction start
Jun 25, 2010(actual)
Construction end
Nov 1, 2010(actual)

Against the original forecast

  • Construction start3 months lateforecast Apr 1, 2010
  • Construction end5 weeks lateforecast Sep 30, 2010

Also in Beckwith