4th Line Trail Construction -Active Transportation
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Beckwith
- Construction start
- Sep 20, 2021(actual)
- Construction end
- Dec 2, 2021(actual)
Against the original forecast
- Construction start3 weeks lateforecast Sep 1, 2021
- Construction end2 months earlyforecast Jan 31, 2022
Also in Beckwith