County Road 23 and County Road 8 Intersection Improvement
Federal contribution
$416,667
Federal share33%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- County of Essex
- Construction start
- Jul 5, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction end10 months lateforecast Dec 30, 2010
Also in Vaughan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30703 in the federal list. How to read these figures.