Millbank Court

Vaughan, Ontario

completeHighways and RoadsISF
Federal contribution
$14,969
Federal share27%

of $55.8K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Vaughan
Construction start
Sep 25, 2009(actual)
Construction end
Jun 30, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Sep 1, 2009
  • Construction end5 months earlyforecast Nov 30, 2010