Back to projects

Kirkbride Crescent

Vaughan, Ontario

completeHighways and RoadsISF
Federal contribution
$6,563
Federal share15%

of $42.4K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Vaughan
Construction start
Sep 1, 2009(actual)
Construction end
Nov 30, 2010(actual)

Against the original forecast

  • Construction end4 months earlyforecast Mar 31, 2011

Also in Vaughan

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30833 in the federal list. How to read these figures.