McClintock Sewage Lagoon Rehabilitation

Algonquin Highlands, Ontario

completeWastewaterISF
Federal contribution
$39,664
Federal share26%

of $150.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jul 2, 2009(actual)
Construction end
Nov 20, 2009(actual)

Against the original forecast

  • Construction end4 months earlyforecast Mar 31, 2010

Also in Algonquin Highlands

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30860 in the federal list. How to read these figures.