Algonquin Highlands Trail Improvements
Federal contribution
$25,000
Federal share37%
of $68.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2016
2016
Built
Approved 13 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Township of Algonquin Highlands
- Construction start
- Mar 15, 2015(actual)
- Construction end
- Dec 28, 2015(actual)
Also in Algonquin Highlands