Back to projects

Sylwood Crescent

Vaughan, Ontario

completeHighways and RoadsISF
Federal contribution
$17,458
Federal share22%

of $77.7K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built

Approved 22 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Vaughan
Construction start
Sep 1, 2009(actual)
Construction end
Oct 31, 2011(actual)

Also in Vaughan

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30863 in the federal list. How to read these figures.