Sicilia Street

Vaughan, Ontario

completeHighways and RoadsISF
Federal contribution
$2,254
Federal share16%

of $13.8K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Vaughan
Construction start
Sep 1, 2009(actual)
Construction end
Nov 30, 2010(actual)

Against the original forecast

  • Construction end4 months earlyforecast Mar 31, 2011